|
|
|
|||
|
SN |
Name of Project |
Name of the client |
Years of completion |
Remarks |
|
A. Office/Hospital/Complex/Hotel Building design, drawing & Construction Supervision |
||||
|
1 |
Detail A/E Design, Drawing of District Education office Building at Okhaldhunga |
Government of Nepal Ministry of Education and Sports, Department of Education (DOE) Sanothimi, Bhaktapur |
Jan, 2014 |
Completed |
|
2 |
Details Architect & Structure design of Library Building at Nursing College, Maharajgunj Ktm |
IOM, Nursing College, Maharajgunj, Ktm. |
Nov. 2014 |
completed |
|
3 |
Detail Design, Drawing, Cost Estimate & Construction Supervision of Hospital building |
Hospital Bulding, New Spinal Cord Injury Ward at INF Green Pastures Hospital, Pokhara, |
Jan, 2013 |
Completed |
|
4 |
A/E Design, drawing, Estimation of Commercial Building Complex at Bhairahawa. |
Nepal Telecome, Central office, Bhadrakali, Kathmandu |
Oct, 2012 |
Completed |
|
5 |
A/E Design, drawing, Estimation & Costing works of Hospital Building at Birtamode Jhapa. |
B&C Medical College Teaching Hospital & Research Center Pvt.Ltd.,Anarmani-3 Birtamode, Jhapa. |
Aug, 2012 |
Completed |
|
6 |
A/E Design, Drawing Estimate & costing works of Hospital Building at Dhapasi,Basundhara,Ringroad |
Kantipur Dental College Teaching Hospital & Research Center,Dhapasi, Basundhara, Ringroad |
June,2012 |
Completed |
|
7 |
A/E Design, Drawing Estimate of OPD & extension of PG Residential Building atTeaching Hospital Area |
T.U,.IOM, B.P. Koirala Lions Center of Ophthalmic Studies, Maharajgung |
Sept, 2012 |
Completed |
|
8 |
A/E Design, drawing & Estimate of office Building & Proposed International Hostel Building at Maharajgung |
IOM, Maharajgunj Medicing Campus at Maharajgunj |
Dec, 2011 |
Completed |
|
9 |
Road design , Building design, Estimate & Supervision at Baluwatar |
Nepal Rastra Bank, Baluwatar |
Oct, 2011 |
completed |
|
10 |
Details survey, Design and Condtruction Supervision of Hotel Bulding Construction Works. |
Government of Nepal, Nepal Academey of Tourism & Hotel Management, Rabibhawan. |
Sept, 2010 |
completed |
|
11 |
Soil Test, Details A/E design and Construction supervision for Asali Mandap Business Building at Naxsal |
Guardian’s Co-operative Society Ltd. (Asali) at Naxsal |
Feb, 2009 |
completed |
|
12 |
Details Structure , A/E design,Soil Test and cost estimate for Campus Building Construction Work at Mitrapark |
Pashupati Multipal Campus, Chabahil, Mitrapark |
Jan, 2008 |
completed |
|
13 |
Soil Test, Details A/E design and Construction supervision for Office & Business Complex at Lazimpat |
Village Travel & Tours (P) Ltd., Lazimpat |
March, 2008 |
completed |
|
14 |
Rubb-Hall Design & Supervision Works |
UN World Food Programme |
Dec, 2007 |
completed |
|
15 |
Building for Handicapped at Kathmandu |
New Life Handicapped and 24 hours Prayer Ministry |
June,2005 |
completed |
|
B. Master Plan, design & drawing |
||||
|
1 |
Preparation of physical infrastructure Master Plan design & drawing at Thapathali branch. |
Nepal Rastra Bank, General Services Department Baluwatar, Kathmandu |
March, 2014 |
completed |
|
2 |
Master Plan, Land Scaping & Design, drawing & estimate of Academic Building |
T.U. IOM,Ayurveda Campus at Kritipur |
Jan, 2013 |
completed |
|
3 |
Master Plan, Soil Test, Details,design,estimate and Construction supervision of Office Building for Nepal Health Professional Council & Nepal Nursing Council at Bansbari, Kathmzndu. |
Nepal Health Professional Council & Nepal Nursing Council at Bansbari, Kathmzndu. |
Dec, 2013 |
Supervision |
|
4 |
Master plan land & Building,Structure Design,Soil Test, Detail Design, drawing and estimation for Commercial Complex Building Construction at Baneshwor |
Citizen Investment Trust, Baneshwor |
Sept, 2012 |
completed |
|
5 |
Master plan land & Building, Details Structure & A/E design of Office Complex Building at Chabahil |
Nepal Telecommunication Authority, Tripureshwor |
Sept, 2012 |
completed |
|
6 |
Conceptual Design, Master Plan of NIDC land at Kathmandu & pokhara |
Nepal Industrial Development Corporation Ltd at Darwarmarg, kathmandu |
Jan, 2011 |
completed |
|
7 |
Master Plan, Architectral & Engineering design, drawing of District Administration office, Khotang |
शहरी तथा भवन निर्माण विभाग |
oct.,2007 |
completed |
|
8 |
Master Plan, Architectral & Engineering design of District Jail, Khotang |
शहरी तथा भवन निर्माण विभाग |
oct.,2007 |
completed |
|
9 |
Master Plan, Architectral & Engineering design of land Revenue office, Dolkha |
शहरी तथा भवन निर्माण विभाग |
oct.,2007 |
completed |
|
10 |
Master Plan, Architectral & Engineering design of District Police office, Arghakhachi |
शहरी तथा भवन निर्माण विभाग |
oct.,2007 |
completed |
|
11 |
Master plan,Survey, & Existing & New system of Sanitory & Drainge System inside Teaching Hospital |
IOM, Office of the Dean, Maharjgunj |
July,2005 |
completed |
|
C. Seismic Vulnerability assignment, Retrofitting Design of Building |
||||
|
2 |
Detail Seismic Vulnerability Assessmen, Detail Design of Retrofitting and Preparation of Cost Estimate of 114 (One Hundred Fourteen) School Building in Kathmandu-48, Lalitpur-22, Bhaktapur-14 , Out of Valley (Banke-5, Bardiya-5, Doti-5, Surkhet-5, Dang-5 and Kailali-5) |
Department of Education, Sanothimi, Bhaktapur |
June, 2014 |
completed |
|
1 |
Detail Seismic Vulnerability Assessmen, Detail Design of Retrofitting and Preparation of Cost Estimate of 20 (Twenty) School Building in Jhapa, Morang, Dhanusha and Parsa. |
Department of Education, Sanothimi, Bhaktapur |
October, 2013 |
completed |
|
2 |
Seismic Vulnerability assignment(for retro fitting) of post Graduate(PG) Residence Doctor’s Quarter Building & Construction Supervision works. |
T.U. IOM,Maharajgunj Medical Campus |
Aug, 2012 |
completed |
|
D. Interior Design, Drawing and Supervision works for Office, Bank Building |
||||
|
1 |
Interior Design works &Cost Estimateof Ministry of Education, Singhdurbar |
Government of Nepal, Ministry of Urban Development Singhdurbar Secretariat Re-construction Committee board. |
April, 2012 |
completed |
|
2 |
Interior Design works &Cost Estimate of Ministry of Local Development, Singhdurbar |
Government of Nepal, Ministry of Urban Development Singhdurbar Secretariat Re-construction Committee board. |
April, 2012 |
completed |
|
3 |
Interior Design of Office Building |
Nepal Rastra Bank, Baluwatar |
July, 2011 |
completed |
|
4 |
Detail interior Design of International Meeting hall & Supervision Works. |
Ministry of Foreign affiar, Kathmandu, Nepal |
Jan., 2010 |
completed |
|
5 |
Interior design & Furniture lyout & desion for Manmohan Cardiothorasic vascular and Transplant Center & ENT, Building at Teaching Hospital Premises. |
Teaching Hospital at Maharjgunj |
March, 2007 |
completed |
|
E . Technical Auditing works |
||||
|
1 |
Ilaka Prahari Karyalaya (APO), Bhandara, Chitwan |
District Police Office, Chitwan |
25th July, 2013 |
completed |
|
2 |
Prahari Chouki (PP), Maidi Dhading |
District Police Office, Dhading |
25th July, 2013 |
completed |
|
3 |
Khajuri Sub-Health Post Building, Dhanusha |
DUDBC, Janakpur |
25th July, 2013 |
completed |
|
4 |
Khajurgachhi Primary Health Center Building, Jhapa |
DUDBC, Ilam |
25th July, 2013 |
completed |
|
5 |
Technical Audit of contract package NVC/TA -01,068/069 District administration office at Dhanagadhi |
DUDBC, Kailali |
July, 2012 |
completed |
|
6 |
Technical Audit of contract package NVC/TA -01,068/069 Kailalai vansar karyalaya at Dhanagadhi |
DUDBC, Kailali |
July, 2012 |
completed |
|
7 |
i)Shree Saileshwori Ma.Vi., Behada, ii) Shree Saraswoti Ma.Vi., Sehari, Beladipur, iii) Shree Rastriya Ma.Vi., Khelad, iv) Shree Rastriya Ma. Vi., Basauti, v) Shree Laxmi Ma. Vi., Udasipur, Kailali |
Depart of Education, Sanothimi, District Education Office, Kailalai |
2013 |
Final Report Submitted |
|
F . Hydro Power Survey & Design |
||||
|
1 |
Middle Gaddi Gad Hydro Power, Doti, Details Design & Estimate |
Triyog Energy & Development (P) Ltd., Maharjgunj |
Oct, 2009 |
completed |
|
2 |
Nayam Nayam Khola Hydro Power Survey, design, drawing Estimate |
Nayam Nayam (Upper) Khola Hydro Power Project, Rasuwa |
Nov-11 |
completed |
|
3 |
Naubise Khola Small HP, Naubise, Detail survey, Design, drawing, Estimate |
Shreerup Hydro Power Project, Kathmandu |
July, 20013 |
completed |
|
G . Valuation Works |
||||
|
1 |
Valutaion of Housing Building & Land. |
Karmachary Sanchaya Kosh , Pulchowlk |
till date |
Continue |
|
2 |
Valutaion of Housing Building & Land. |
Bank Of Kathmandu, Kamaladi |
till date |
Continue |
|
3 |
Valutaion of Housing Building & Land. |
Agriculture Development Bank, Kathmandu |
till date |
Continue |
|
4 |
Valutaion of Housing Building & Land. |
Rastrya Banijya Bank, Kathmandu |
till date |
Continue |
|
5 |
Valutaion of Housing Building & Land. |
Citizenn’s Bank International, Kamaladi, Kathmandu |
till date |
Continue |
|
6 |
Valutaion of Housing Building & Land. |
Bright Development Bank.Panauti, Kavre, Nepal |
till date |
Continue |
|
7 |
Valutaion of Housing Building & Land. |
Nepal Housing Development Finance Company Ltd. New Baneshwor |
till date |
Continue |
|
8 |
Valutaion of Housing Building & Land. |
NCC Bank, NB Building, Bagbazar |
till date |
Continue |
|
9 |
Valutaion of Housing Building & Land. |
NIDC, Darbarmarg, Kathmandu |
till date |
Continue |
|
10 |
Valutaion of Housing Building & Land. |
Royal – Rara – Api Joint Merger Committee Secretariat, Sita Kuti, Durbar Marg, Kathmandu |
2013 |
completed |
|
11 |
Valutaion of Housing Building & Land. |
Siddhartha Development Bank Ltd & Public Development Bank Ltd Joint Merger Committee Secretariat |
2013 |
completed |





